WSC status and schedule
Updated on Mon, 2009-10-19 14:36. Originally created by surrow on 2009-10-19 14:31.Reference
Speaker : Jason Bessuille ( MIT )
Talk time : 15:30, Duration : 01:00
Integration: Status of Thermal model tests
Updated on Mon, 2009-10-19 14:38. Originally created by surrow on 2009-10-19 14:30.Reference
Speaker : James Hays-Wehle ( MIT )
Talk time : 15:00, Duration : 00:30
Beta Gamma+Jet Finder Code
Code Location: /star/u/aliceb/PhotonJet/Beta
What does it do:
DAQ: Production readiness - (ARC/ARM)
Updated on Wed, 2009-10-28 16:03 by gvisser. Originally created by surrow on 2009-10-19 14:29.Reference
Speaker : Gerard Visser ( IUCF )
Talk time : 14:00, Duration : 01:00
Lunch Break
Updated on Mon, 2009-10-19 14:27. Originally created by surrow on 2009-10-19 14:26.Reference
Talk time : 12:30, Duration : 01:30
FEE: Production readiness - APV board (Compunetics / Bonding)
Updated on Mon, 2009-10-19 14:25. Originally created by surrow on 2009-10-19 14:25.Reference
Speaker : Ben Buck ( MIT )
Talk time : 12:00, Duration : 00:30
Coffee Break
Updated on Mon, 2009-10-19 14:23. Originally created by surrow on 2009-10-19 14:23.Reference
Talk time : 10:30, Duration : 00:30
Triple-GEM: Production readiness - Lab preparation (LNS / Bates)
Updated on Mon, 2009-10-19 14:23. Originally created by surrow on 2009-10-19 14:21.Reference
Speaker : Bernd Surrow / Jason Bessuille ( MIT )
Talk time : 11:30, Duration : 00:30
Triple-GEM: Production readiness - 2D readout board
Updated on Wed, 2009-10-21 08:02. Originally created by surrow on 2009-10-19 14:17.Reference
Speaker : Doug Hasell ( MIT )
Talk time : 11:00, Duration : 00:30
Triple-GEM: Production readiness - GEM foils (Scans / HV tests)
Updated on Wed, 2009-10-21 10:14 by wleight. Originally created by surrow on 2009-10-19 14:14.Reference
Speaker : Will Leight / Ross Corliss ( MIT )
Talk time : 10:00, Duration : 00:30
Triple-GEM: Production readiness - Chamber mechanics (Frames / HV box / Jigs etc.)
Updated on Mon, 2009-10-19 14:19. Originally created by surrow on 2009-10-19 14:13.Reference
Speaker : Jason Bessuille ( MIT )
Talk time : 09:30, Duration : 00:30
FGT Schedule / Funding
Updated on Mon, 2009-10-19 14:13. Originally created by surrow on 2009-10-19 10:59.Reference
Speaker : Bernd Surrow ( MIT )
Talk time : 09:00, Duration : 00:30
Shift sign-up addtitional functional requirements for FY10
General
The shift sign-up was revamped following the description of changes in STAR Notes PSN0482 : STAR PhoneBook and shift accounting - Definitions and development plan.
FGT Meeting at MIT
Updated on Mon, 2009-10-19 09:13. Originally created by balewski on 2009-10-19 09:13.MIT, at 13:00 (GMT), duration : 00:00
Time | Talk | Presenter |
---|---|---|
09:00 | FGT Schedule / Funding ( 00:30 ) 0 files | Bernd Surrow (MIT) |
09:30 | Triple-GEM: Production readiness - Chamber mechanics (Frames / HV box / Jigs etc.) ( 00:30 ) 0 files | Jason Bessuille (MIT) |
10:00 | Triple-GEM: Production readiness - GEM foils (Scans / HV tests) ( 00:30 ) 1 file | Will Leight / Ross Corliss (MIT) |
10:30 | Coffee Break ( 00:30 ) 0 files | |
11:00 | Triple-GEM: Production readiness - 2D readout board ( 00:30 ) 1 file | Doug Hasell (MIT) |
11:30 | Triple-GEM: Production readiness - Lab preparation (LNS / Bates) ( 00:30 ) 0 files | Bernd Surrow / Jason Bessuille (MIT) |
12:00 | FEE: Production readiness - APV board (Compunetics / Bonding) ( 00:30 ) 0 files | Ben Buck (MIT) |
12:30 | Lunch Break ( 01:30 ) 0 files | |
14:00 | DAQ: Production readiness - (ARC/ARM) ( 01:00 ) 2 files | Gerard Visser (IUCF) |
15:00 | Integration: Status of Thermal model tests ( 00:30 ) 0 files | James Hays-Wehle (MIT) |
15:30 | WSC status and schedule ( 01:00 ) 0 files | Jason Bessuille (MIT) |
Linear Fit of Time Dependency in BEMC Gains
To better characterize the time-dependence in the BEMC in 2006, we have fit each of the gains versus time data sets for each eta bin with a linear (non-constant) fit.
Minutes
Updated on Fri, 2009-10-16 20:43. Originally created by margetis on 2009-10-16 20:00.Reference
Talk time : 12:30, Duration : 00:20
1) Updates on current CDR still on. Will include part of
CD0 response paper (Failure analysis, thin/thick studies)
Efficiency as a function of Eta, Vz
Because of the asymmetric VZ distribution (shifted toward negative VZ) and limited EMC acceptance (west barrel only), there's a moving turn-on for the electron identification
proposed abstract for 2010 APS
Attached is my proposed abstract for the APS meeting next spring. (note the most recent version is now v5, incorporating comments from Ernst and Jim)
Abstract for APS 2010
See Attachements. Please select the last file (ie most recent version).