Some Additional band in dEdx vs p distribution in AuAu 200 RFF
I see some additional band in dEdx vs p distribution in AuAu 200 RFF(the left down corner).
Geometry Update/Prototype acceptance/efficiency
Updated on Sun, 2011-10-09 12:25 by bouchet. Originally created by margetis on 2011-10-05 13:22.jan - DB layout , charge sharing
Updated on Wed, 2011-10-05 09:53. Originally created by balewski on 2011-10-05 09:12.Reference
Talk time : 10:00, Duration : 00:20
AOB
Updated on Wed, 2011-10-05 10:58. Originally created by jeromel on 2011-10-05 08:48.Speaker : All ( All )
Talk time : 12:40, Duration : 00:20
- SUMS: The Action element
- ...
TpcRS updates, improvements on dE/dx
Updated on Wed, 2011-10-05 11:28. Originally created by jeromel on 2011-10-05 08:48.Speaker : Yuri Fisyak ( BNL )
Talk time : 12:20, Duration : 00:20
See You do not have access to view this node for more information.
Calibration updates, Run 11 and looking forward
Updated on Wed, 2011-10-05 09:31 by gdwebb. Originally created by jeromel on 2011-10-05 08:44.Speaker : Grant Webb ( UKY )
Talk time : 12:00, Duration : 00:20
Software and Computing Meeting
1-189, EVO, at 16:00 (GMT), duration : 01:00
Time | Talk | Presenter |
---|---|---|
12:00 | Calibration updates, Run 11 and looking forward ( 00:20 ) 2 files | Grant Webb (UKY) |
12:20 | TpcRS updates, improvements on dE/dx ( 00:20 ) 0 files | Yuri Fisyak (BNL) |
12:40 | AOB ( 00:20 ) 1 file | All (All) |
End game
Updated on Tue, 2011-10-04 15:53. Originally created by wlodek on 2011-10-04 15:53.Fiducial cuts revisited ...
Updated on Wed, 2011-10-05 08:51 by yipkin. Originally created by jhlee on 2011-10-04 14:18.Final re-alignment...
Updated on Tue, 2011-10-04 14:17. Originally created by jhlee on 2011-10-04 14:17.HFT Software
Updated on Thu, 2011-10-20 11:06. Originally created by margetis on 2011-10-04 09:19.510-4867333, at 17:30 (GMT), duration : 01:00
1) I updated the TPC-PXL sector overlap picture to reflect
the true TPC arrangement, as per Xin's correction. I
put the new picture in the meeting's Drupal page.
2) Flemming drafted a MS-Project schedule diagram for software
and associated Milestones. I will at this in detail over
the weekend.
3) Flemming is preparing some drawings of the detector complex
for the non-initiated folks, like me.
4) Jonathan is looking into tracking efficiency/ghosting with the
prototype only. He has problems with every option he tries
for the moment (some of them just resolved). There is going
to be more discussion in this list about this stuff. It
has been a while since we used this production chains and
things got rusted.
5) I have asked for CMM time during the Collab. meeting since
we are going to be there anyway.
6) I 've contacted Auguste about the slow simulator.
7) Jerome contacted me about updates. We are on in next week's
S&C Wed meeting and also during the Friday morning plenary
session at the Collab. meeting.
Time | Talk | Presenter |
---|---|---|
13:30 | Geometry ( 00:05 ) 2 files | |
13:35 | Minutes ( 00:20 ) 0 files |
HFT Software
Updated on Fri, 2011-10-28 09:05. Originally created by margetis on 2011-10-04 09:19.510-4867333, at 17:30 (GMT), duration : 01:00
1) Geometry. Flemming produced a proportional sketch of the
support structures. Posted it on Drupal's page.
2) Prototype tracking. Jonathan is getting close. He might
post a couple of plots by the meeting's time.
3) PXL response. We got the DIGMAP code and some docs. What
next?
4) The CERN beam test is successfully over. I put a picture
he sent on Drupal
Time | Talk | Presenter |
---|---|---|
12:30 | Geometry ( 00:20 ) 1 file | |
12:50 | prototype tracking ( 00:20 ) 1 file | |
13:10 | Minutes ( 00:20 ) 1 file |
HFT Software
Updated on Fri, 2011-11-04 12:30. Originally created by margetis on 2011-10-04 09:19.510-4867333, at 17:30 (GMT), duration : 01:00
1) I made a short presentation at the S&C meeting yesterday:
http://drupal.star.bnl.gov/STAR/event/2011/11/02/software-and-computing-meeting/hft-software-status
2) Jonathan made progress on TPC+PXL tracking.
3) I got an email form Howard that the touch probe for the
VIEW-3000 will ship Nov 11. There is no arrival date but
we might be able to do something with it at the Collab.
meeting. If not we will still learn about data formats
etc of this device.
Time | Talk | Presenter |
---|---|---|
12:30 | [very] preliminary look at the pixel patch efficiency ( 00:10 ) 2 files | jonathan |
HFT Software
Updated on Fri, 2011-10-14 11:55. Originally created by margetis on 2011-10-04 09:19.510-4867333, at 17:30 (GMT), duration : 01:00
1) I know that Jonathan re-run the prototype
efficiency (acceptance) for pt>0.3
(which is to make sure we have a reasonable
track reconstr.in the TPC). He is going to post
his file soon.
2) We are looking into optimizing the TPC+3sector PXL
configuration. TPC has 12 sectors the PXL 3 out of 10.
We need to take care of the gaps (put the 3sectors)
so we have only one TPC gap shadowing, and also make
sure we have healthy TPC sectors. He has some drawings
and there is work in progress here (use TPC state in last
run as a basis).
3) He is making a list of volumes in Y2013 'blank' geometry.
We are waiting for a drawing to be available for that
year's support material but Flemming/Jim are big helpers
in this (thanks guys). Jonathan is playing with this
geometry.
4) There is some progress in reprocessing the old, Yifei's
files with BFC and mask out IST/SSD hits (no material)
plus PXL sector (hits). Later I will coordiante with
Yifei to start a production with Hijing+D0s in Y2013a,b
(a=Mercedes, b=All adjacent) with proper material, for
accurate tracking excercises.
5) I posted a WBS Software schedule Flemming prepared. I
still need to talk to him so I can understand the notation.
Send the list the items yoiu might have. S.
Time | Talk | Presenter |
---|---|---|
12:30 | Minutes ( 00:20 ) 1 file | |
13:00 | WBS ( 00:10 ) 1 file | |
13:20 | Geometry acceptance update ( 00:10 ) 3 files | jonathan |
HFT Software
Updated on Thu, 2011-10-06 17:09. Originally created by margetis on 2011-10-04 09:18.510-4867333, at 17:30 (GMT), duration : 01:00
1) HFT Geometry update. There several things going on.
The highest priority item is to build a y2013 geometry
for the prototype run. This needs the beam pipe, the
support cones and the 3-sector PXL model. I asked
Jonathan to be the liaison with the BNL group.
The SSD ladders in geant have very nice detail (thanks
Gerrit for remind me of that). Minor work on the ladder
would be needed plus the re-mounting in the smaller
radius.
Some documents I posted on the meeting's page, Jonathan
is going to also post snapshots of UPGR13 and UPGR15
(current) geometry.
I will created on the subsystem pages on Drupal directories
(repositories) for Geometry information/drawing, Survey
documents (eg fiducial mark position drawings etc) etc.
2) We started work on updating the prototype efficiency/
acceptance of D0s to current sector specs. Some
older calculations done by us and Howard Wieman are
posted. This stuff is going to be the basis for a
presentation to the HF group with the question of
'What physics can we get out of the HFT prototype?'
provided a lengthy/healthy run and also that
tracking with TPC/PXL only is marginally o.k. (TBD)
3) I would like to start the discussion (Purdue needed)
on what is next in implementing a Fast/slow sim in STAR.
Time | Talk | Presenter |
---|---|---|
13:30 | Geometry Update/Prototype acceptance/efficiency ( 00:15 ) 9 files | All |
13:45 | geometry dev13 ( 00:20 ) 1 file | jonathan |
14:05 | Minutes ( 00:20 ) 1 file |