FGT Weekly Meeting
Updated on Fri, 2012-09-21 09:54. Originally created by surrow on 2012-09-21 07:55.BNL , at 15:00 (GMT), duration : 00:00
Agenda:
1) 2012 1st phase installation: Xuan / Bernd / Jason
2) DAQ (ARC / ARM status) : Gerard et al.
3) Production of remaining quarter sections : Jason / Bernd
4) Summary of software activities : Anselm et al.
5) AOB : ALL
EVO-------------------------------------------------------------------------------------------
People can connect via EVO (use the following link):
http://evo.caltech.edu/evoNext/koala.jnlp?meeting=e9eIeivevta2aiIaaaI9
The password is fgtin2011
You can also connect via phone. Phone bridge numbers can be found at:
http://evo.caltech.edu/evoGate/Documentation/telephone.jsp
The meeting ID is 14 1479 and password 9215.
You can also connect via Skype by adding "evo.phone" (without the
quotes) to your buddy list and calling that contact. Meeting ID and
password are the same as above.
EVO-------------------------------------------------------------------------------------------
Time | Talk | Presenter |
---|---|---|
11:00 | ARM & ARC status and inventory ( 00:01 ) 2 files | gerard |
TPC charge distribution fit to power law
For many years, we have used the following distribution to model space charge in the TPC, taken from StRoot/StDbUtilities/StMagUtilities.cxx:
K+ (for Phi) in run 10 Au+Au 7.7 GeV
Updated on Wed, 2012-09-19 09:56. Originally created by zhux on 2012-09-19 09:56.K+ (for Phi) in run 10 Au+Au 11.5 GeV
Updated on Wed, 2012-09-19 09:54. Originally created by zhux on 2012-09-19 09:54.Minbias Trigger (310014)
Library: SL10h
flat pT: [0, 5] GeV
flat Eta: [-1.1, 1.1]
VertexZ: [-50, 50] cm
Vr < 2 cm
Events: 500 K
No. of Kaon+ per event: 5% remult
Request ID | 20123803 |
Priority: EC | 0 |
Priority: pwg | Normal |
Status | New |
Physics Working Group | Light Flavor Spectra |
Requested by | zhux |
Contact email(s) | zhux@tsinghua.edu.cn, xpzhangnju@gmail.com |
Contact phone(s) | |
PWG email(s) | lfspectra-hn@www.star.bnl.gov |
Assigned Deputy: | Not assigned |
Assigned Helper: | Not assigned |
File lookup |
Particle | Alpha |
Particle settings | dalitz |
Particles per event | 1 |
Vertex Z, cm | -30 < Vertex < 30 |
Gaussian sigma in X,Y,Z (cm), if applicable | 0, 0, 0 |
Vertex offset: x, mm | 0 |
Vertex offset: y, mm | 0 |
Φ (phi), radian | 0 < Φ < 6.29 |
η (eta) | -0.5 < η < 0.5 |
Pt, GeV | 0 < Pt < 30 |
K+ (for Phi) in run 10 Au+Au 39 GeV
Updated on Wed, 2012-09-19 09:51. Originally created by zhux on 2012-09-19 09:51.Minbias Trigger (280001, 280002)
Library: SL10k
flat pT: [0, 5] GeV
flat Eta: [-1.1, 1.1]
VertexZ: [-40, 40] cm
Vr < 2 cm
Events: 500 K
No. of Kaon+ per event: 5% remult
Request ID | 20123802 |
Priority: EC | 0 |
Priority: pwg | Normal |
Status | New |
Physics Working Group | Light Flavor Spectra |
Requested by | zhux |
Contact email(s) | zhux@tsinghua.edu.cn, xpzhangnju@gmail.com |
Contact phone(s) | |
PWG email(s) | lfspectra-hn@www.star.bnl.gov |
Assigned Deputy: | Not assigned |
Assigned Helper: | Not assigned |
File lookup |
Particle | Alpha |
Particle settings | dalitz |
Particles per event | 1 |
Vertex Z, cm | -30 < Vertex < 30 |
Gaussian sigma in X,Y,Z (cm), if applicable | 0, 0, 0 |
Vertex offset: x, mm | 0 |
Vertex offset: y, mm | 0 |
Φ (phi), radian | 0 < Φ < 6.29 |
η (eta) | -0.5 < η < 0.5 |
Pt, GeV | 0 < Pt < 30 |
Improving results on transerve double spin asymmetries in the CNI region at STAR
Updated on Wed, 2012-09-19 09:14. Originally created by yipkin on 2012-09-19 09:07.Reference
Speaker : Dima Svirida
Talk time : 09:00, Duration : 00:20
Dima's talk:
Upsilon 1s,2s,3s in p+p Run 9
Updated on Mon, 2013-01-21 12:00 by mstftsm. Originally created by bielcik on 2012-09-18 07:33.----------------------------------------- p+p 200 GeV (year 2009) fast stream data st_upsilon 30K events for each states (1s, 2s, 3s) flat in pT and y: pT= 0 - 10 GeV/c y= -2.0 - 2.0 no VertexZ cut 1 Upsilon per event let the Upsilon decay only into e+e- production version: P11id match data starver: SL11d geant geometry option: y2009 ------------------------------------------
Request ID | 20123801 |
Priority: EC | 0 |
Priority: pwg | Normal |
Status | Closed |
Physics Working Group | Heavy Flavor |
Requested by | bielcik |
Contact email(s) | akesich@gmail.com, jaroslav.bielcik@fjfi.cvut.cz |
Contact phone(s) | |
PWG email(s) | heavy-hn@www.star.bnl.gov |
Assigned Deputy: | Not assigned |
Assigned Helper: | Not assigned |
Request type: | Standard Embedding request (particle in real events) |
Number of events | 30000 = 30 K |
Magnetic Field | Full-Field |
Collision Type | dau 200GeV |
Centrality | ---- SELECT CENTRALITY ---- |
BFC tags | st_upsilon |
Production | ---- SELECT PRODUCTION TAG ---- |
Geometry: simu | |
Geometry: reco | |
Library | SL11d_embed |
Vertex option | Force vertex as MC vertex |
Pileup option | No |
Detector Set |
File lookup |
Particle | Upsilon1S |
Particle settings | Flat in Pt |
Particles per event | 1 |
Vertex Z, cm | -150 < Vertex < 150 |
Gaussian sigma in X,Y,Z (cm), if applicable | 0, 0, 0 |
Vertex offset: x, mm | 0 |
Vertex offset: y, mm | 0 |
Φ (phi), radian | 0 < Φ < 6.39 |
η (eta) | -2 < η < 2 |
Pt, GeV | 0 < Pt < 10 |
eSTAR
Updated on Mon, 2012-10-01 09:38. Originally created by xzb on 2012-09-17 10:54.EVO 14 3853 (Tuesday 10/02 noon), at 16:00 (GMT), duration : 01:00
Agenda:
1) Update on FCS
a) physics drives
(diject correlation mapping of CGC boundary)?
use in Heavy-ion runs (lighter ions?)
b) simulations
c) proposal (LoI)?
2) update on iTPC
a) simulation of tracking (Hui et al.)
different padrow configurations
b) proposal
Technically driven schedule
http://drupal.star.bnl.gov/STAR/system/files/STAR_iTPC_technical_schedule_09242012.pdf
DOE (3-4M$?)
possible 3 subprojects:
electronics (DOE) , East (NNSFC?), West(NSF associated with EEMC?)
need engineer cost estimate ;
proposal section contributions;
c) request for iTPC R&D in FY13 (Jim) (~200K$?)
i) design/build a prototype Aluminum Strongback (can we also reduce material)
ii) optimize pad sizes
iii) lab testing of the new pad and wire geometry
iv) winding machine setup/prototyping at IU(?)
v) Super-ALTRO prototyping and design for FEE
3) next EIC R&D calls
https://wiki.bnl.gov/conferences/index.php/EIC_R%25D
Deadline: October 26, 2012 (presentation around November 22, 2012)
4) STAR Analysis and Upgrade Meeting, Nov. 28 - Dec. 2, 2012, UCLA
5) other items
Ernst & Zhangbu
eSTAR
Updated on Tue, 2012-09-18 10:53. Originally created by xzb on 2012-09-17 10:54.EVO 14 3853 (Tuesday 09/04 noon), at 16:00 (GMT), duration : 01:00
Agenda:
1) Update on FCS
a) physics drives
(diject correlation mapping of CGC boundary)?
use in Heavy-ion runs (lighter ions?)
b) simulations
c) proposal (LoI)?
2) update on iTPC
a) simulation of tracking (Hui et al.)
b) proposal
DOE (3-4M$?)
possible 3 subprojects:
electronics (DOE) , East (NNSFC?), West(NSF associated with EEMC?)
need engineer cost estimate ;
proposal section contributions;
3) test beam proposal calls
http://www.star.bnl.gov/HyperNews-star/protected/get/estar/117.html
4) next EIC R&D calls
https://wiki.bnl.gov/conferences/index.php/EIC_R%25D
Deadline: October 26, 2012 (presentation around November 22, 2012)
5) STAR Analysis and Upgrade Meeting, Nov. 28 - Dec. 2, 2012, UCLA
6) other items
Ernst & Zhangbu
STAR Inner Detector Support pictures Sept 2012
A couple of pictures by BNL photography after IDS was lifted to platform.
dev14 misalignment
Updated on Fri, 2012-09-14 11:20. Originally created by bouchet on 2012-09-14 11:20.Reference
Speaker : jonathan
Talk time : 12:50, Duration : 00:20
- look at the Stipulls data when 1 PXL sector is shifted along Z axis by 1 cm
The batch general queue allows your jobs to run on PHENIX nodes. How important is this feature to you?
Updated on Thu, 2012-09-13 16:37 by testadmin. Originally created by jeromel on 2012-09-13 16:33.FGT Event Display screenshots
Status Update: The FGT geometry and pedistal values are now being read from the common database. Everything still works just fine.
STAR Management Weekly Meeting
BNL, Buld 510, I-189, at 16:00 (GMT), duration : 01:00
STAR Management Weekly Meeting
BNL, Buld 510, I-189, at 16:00 (GMT), duration : 01:00
EVO: Title: STAR Management Weekly Meeting // Community: STAR // Password: star
http://evo.caltech.edu/evoNext/koala.jnlp?meeting=ete8eavBv9atauIiaiIt
Phone Bridge: +1 626 395 2112 (CA) / +1 631 344 6100 (NY) // ID: 143875 // Password: 0952
Time: 12 - 13 EDT
*--===================================================================--*
I. Agenda:
1) News: (a) WAH; (b) Run12 W-plot
2) QM12 proceedings QA: Xin
3) Update on FGT/HFT/ Upgrade review: Flemming
4) Spin co-convener: Nu
5) TBD
*--===================================================================--*
II. Brief Summary and action Items:
1) Attandance: Carl, Xin, Bedanga, Huan, Nu, Jamie, Flemming, Jerome, Gene.
2) Run12 W-plot: It is ready for public. Will appear in DNP talks by Renee, Jan, Elke, Carl. Jamie will contact BNL // MTD installation started at the WAH
3) QM proceedings: Till yesterday we have 19 out of 20 parallel QM drafts. The missing PA is remined. / UU results have been rechecked. / Invited
4) Upgrade: Flemming. (a) FGT almost all 4 Quadrants By Nov. 6th. No news on the cosmic ray tests. S. Steadmann presented a plan, budget/progress are
on track. Needs more effort on software. (b) HFT: next Tuesday review. LBNL will take care of the electronics and production. DOE NP has been informed.
Tom wants a technical review of the HFT project, sometime next January. BNL led review. (c) R&D meeting: Hank's/iTPC/HLT/FCal, Xin/Wei/Dick/..
no guidence from BNL yet.
III. Note:
► 2012 RHIC/AGS Thesis Award: Congratulations to Len Eun, full citation.
► Charges to eSTAR Task Force, co-Chairs: Ernst Sichtermann and Zhangbu Xu
► STAR FMS Review: Sept. 1-2, BNL. P. Jacobs (chair). Review Report
*--===================================================================--*
IV. Future Meetings and Reviews:
► QCD Phase Structure I, Wuhan, October 7-20, 2012
► STAR Regional Meeting, Warsaw, Poland, November 5-7, 2012
► STAR Analysis and Upgrade Meeting, UCLA, November 28 - December 2, 2012
► STAR Collaboration Meeting, BNL, February 25 - March 1, 2013
STAR Management Weekly Meeting
BNL, Buld 510, I-189, at 16:00 (GMT), duration : 01:00
EVO: Title: STAR Management Weekly Meeting // Community: STAR // Password: star
http://evo.caltech.edu/evoNext/koala.jnlp?meeting=ete8eavBv9atauIiaiIt
Phone Bridge: +1 626 395 2112 (CA) / +1 631 344 6100 (NY) // ID: 143875 // Password: 0952
Time: 12 - 13 EDT
*--===================================================================--*
I. Agenda:
1) News: () Fix-target; NU (a) Next collaboration meeting date; (b) Trigger board chair: Nu
2) STAR whitepaper-II: Bedanga
3) QM12 proceedings QA: Xin
4) Upgrade projects (HLT/iTPC/FCal/pp2pp-IIa): Flemming/Huan
5) Spin co-convener: Nu
*--===================================================================--*
II. Brief Summary and action Items:
1) Attandance:Jamie, Gene, Jerome, Flemming, Xin, Carl, Huan, Bedanga, Nu, Scott,
2) Spin Contribution to Tribble Committee: STAR results on (a) Run9 di-jets; (b) Ws from Run12; Spin PWG signed off for QCDn and DNP; (c)
3) Upgrades: Flemming&Huang will setup a meeting in Oct. to discuss upgrades. In the mean time, we request CAD to make the estimate for pp2pp IIa.
4) FGT installation:
5) HFT: LBNL takes over SSD electronics, intention to early coopletion. DIscussed with DOE, no strong disagreement. More review may be needed. LBNL is ready for
pixel production for Run13. End January sectors will be ready. Platform insertation test, Oct. 20-30.
6) Fixed-target: include SOP in the discussions.
III. Note:
► 2012 RHIC/AGS Thesis Award: Congratulations to Len Eun, full citation.
► Charges to eSTAR Task Force, co-Chairs: Ernst Sichtermann and Zhangbu Xu
► STAR FMS Review: Sept. 1-2, BNL. P. Jacobs (chair). Review Report
*--===================================================================--*
IV. Future Meetings and Reviews:
► QCD Phase Structure I, Wuhan, October 7-20, 2012
► STAR Regional Meeting, Warsaw, Poland, November 5-7, 2012
► STAR Analysis and Upgrade Meeting, UCLA, November 28 - December 2, 2012
► STAR Collaboration Meeting, BNL, February 25 - March 1, 2013
STAR Management Weekly Meeting
BNL, Buld 510, I-189, at 16:00 (GMT), duration : 01:00
EVO: Title: STAR Management Weekly Meeting // Community: STAR // Password: star
http://evo.caltech.edu/evoNext/koala.jnlp?meeting=ete8eavBv9atauIiaiIt
Phone Bridge: +1 626 395 2112 (CA) / +1 631 344 6100 (NY) // ID: 143875 // Password: 0952
Time: 12 - 13 EDT
*--===================================================================--*
I. Agenda:
iTPC DIscussions:
Note from Jim/Zhangbu:
1.) Organize the project, recover lost & retired skills. Review available drawings and documentation. Arrange for best available manpower
and write contracts with institutions. 6 FTE months.
2.) Mechanical design: a.) Strongback - 6 FTE months b.) Pad Plane (mechanical) - 3 FTE months
c.) Grids and Wire Factory design and layout - 6 FTE months
These activities can be done in series or in parallel, depending on available human resources.
3.) Electrical design: a.) Pad Plane (electrical) - 3 FTE months b.) FEE - 6 FTE months (need input from Tonko, ignores problem with sAltro)
c.) RDO - 6 FTE months (need input from Tonko, ignores problem with sAltro)
These activities can be done in series or in parallel, depending on available human resources.
4.) Cooling - 3 FTE months
5.) Mechanical Fabrication a.) Strongback - 3 months duration at outside shop plus time to write and sign contract. Guesstimate 15K per sector.
b.) Grids - 1 year duration. Need to build small factory. 3 Techs fulltime.
6.) Electrical Fabrication a.) Pad plane - 3 months duration at outside shop plus time to write and sign contract. Guesstimate 5K per sector.
b.) FEE - less than 1 year duration. Guesstimate 750K for all Fee's.
c.) RDO - less than 1 year duration. Guesstimate 500k for all RDO's.
7.) Installation a.) Mechanical - 3 months duration. 3 techs full time. b.) Electrical - 3 months duration. 3 techs full time.
This plan assumes that the Sector Installation tool will be paid for by STAR operations. Further, it is assumed that the Sector Installation tool
design will be completed in the summer of 2013; fabricated and safety approved and tested before the summer of 2014. Finally one or more
sectors must be installed and tested with the new sector installation tool before we install the full iTPC upgrade. So if the tool is ready for use in
the summer of 2014, we install one sector (sector 20?) and test it in the subsequent run. Assuming success, this means the iTPC upgrade can
be installed in the summer of 2015 (for run 16).
So with a dedicated and efficient team, the iTPC upgrade can be completed in a duration of 3 years ... but this is fairly fast paced and it assumes
that the very best people are ready and available to work on the project.
45% contingency is about the maximum that Physicists will allow and the minimum that the DOE will accept for a project at this stage of development ;-)
Grand Total: 2 Million labor + 1.75 Million Fabrications + 45% = $5.4M
Duration: 3 years
*--===================================================================--*
II. Brief Summary and action Items:
III. Note:
► 2012 RHIC/AGS Thesis Award: Congratulations to Len Eun, full citation.
► Charges to eSTAR Task Force, co-Chairs: Ernst Sichtermann and Zhangbu Xu
► STAR FMS Review: Sept. 1-2, BNL. P. Jacobs (chair). Review Report
*--===================================================================--*
IV. Future Meetings and Reviews:
► SPIN2012, Dubna, Russia, September 17-22, 2012
► QCD Phase Structure I, Wuhan, October 7-20, 2012
► STAR Regional Meeting, Warsaw, Poland, November 5-7, 2012
► STAR Analysis and Upgrade Meeting, UCLA, November 28 - December 2, 2012
► STAR Collaboration Meeting, BNL, February 25 - March 1, 2013
STAR Management Weekly Meeting
BNL, Buld 510, I-189, at 16:00 (GMT), duration : 01:00
EVO: Title: STAR Management Weekly Meeting // Community: STAR // Password: star
http://evo.caltech.edu/evoNext/koala.jnlp?meeting=ete8eavBv9atauIiaiIt
Phone Bridge: +1 626 395 2112 (CA) / +1 631 344 6100 (NY) // ID: 143875 // Password: 0952
Time: 12 - 13 EDT
*--===================================================================--*
I. Agenda:
1) News: (a) Tribble subcommittee meeting: Nu [Talks: Bill Zajc, Steve Vigdor1, Urs Wiedemann, Steve Vigdor2]
2) STAR whitepaper-II: Bedanga
3) QM QA and Proceedings: Xin
4) Rotatiion Spin PWG co-convener: Nu (2 candidates)
5) Next collaboration meeting: Feb. 11-15?
*--===================================================================--*
II. Brief Summary and action Items:
1) Attandance:Bedanga, Flemming, Scott, Xin, Carl, Huan, Jerome, Nu
2) Tribble subcommittee discussion:
3) ReviewPaper (WhitePaper): Bedanga: more report next week. New W-analysis show good progress. Inclusive and di-jets results are consist
4) QM proceedings QA: Xin. Discussions among co-conveners and PAC. Results on UU, HBT, Fluctuation (DCC search): QA in health progress,
value is between (0.99, 1), systematic error is important, both East and West FTPCs should be checked; need more people on HBT related analysis.
5) Meeting dates: It was Feb. 24-March 1, 2013. Gary requested the change. // No meeting next week.
6) Trigger Board: one candidatenow. We are also starting preparation for Run13. Will be discuss on the Sept. 24 meeting.
III. Note:
► 2012 RHIC/AGS Thesis Award: Congratulations to Len Eun, full citation.
► Charges to eSTAR Task Force, co-Chairs: Ernst Sichtermann and Zhangbu Xu
► STAR FMS Review: Sept. 1-2, BNL. P. Jacobs (chair). Review Report
*--===================================================================--*
IV. Future Meetings and Reviews:
► SPIN2012, Dubna, Russia, September 17-22, 2012
► QCD Phase Structure I, Wuhan, October 7-20, 2012
► STAR Regional Meeting, Warsaw, Poland, November 5-7, 2012
► STAR Analysis and Upgrade Meeting, UCLA, November 28 - December 2, 2012
► STAR Collaboration Meeting, BNL, February, 2013
pT_trigFired_run12046105
Updated on Thu, 2012-09-13 12:37. Originally created by drach09 on 2012-09-13 12:37.BNL-team involvement
Updated on Fri, 2012-09-14 17:28. Originally created by margetis on 2012-09-13 10:30.Reference
Talk time : 12:30, Duration : 00:20