Executive session with the commitee only

Speaker : Reviewers


Talk time : 16:00, Duration : 00:30

Discussions

Speaker : All


Talk time : 15:30, Duration : 00:30

Trigger system/QT boards status and future plan

Speaker : Hank Crawford


Talk time : 14:50, Duration : 00:20

DEP for EPD

Speaker : Tonko Ljubicic


Talk time : 14:30, Duration : 00:20

Lunch Break

Speaker : All


Talk time : 12:20, Duration : 02:10

People, Cost, Timeline

Speaker : Alexander Schmah


Talk time : 11:50, Duration : 00:25

 

Final Design

Speaker : Alexander Schmah


Talk time : 11:25, Duration : 00:25

Results from R&D Phase

Speaker : Alexander Schmah


Talk time : 10:35, Duration : 00:25

Requirements and Simulation

Speaker : Alexander Schmah


Talk time : 10:10, Duration : 00:25

EPD Physics

Speaker : Alexander Schmah


Talk time : 09:45, Duration : 00:25

Run14 vertex resolution

Speaker : Bingchu Huang


Talk time : 12:20, Duration : 00:20

 

Run14 st_physics data reproduction request and VF parameter test

Speaker : Guannan/Mustafa/Xin


Talk time : 12:00, Duration : 00:20

 https://drupal.star.bnl.gov/STAR/blog/dongx/run14-stphysics-data-repr

S&C Offline Software

2016-04-07 16:00
2016-04-07 17:00
America/New York
Thursday, 7 April 2016
1-165, SRN, at 20:00 (GMT), duration : 01:00
SRN ID: 1096183

EVO Phone Bridge Telephone Numbers:
---------------
- USA (BNL, Upton, NY)
+1 631 344 6100

- USA (Caltech, Pasadena, CA)
+1 626 395 2112
TimeTalkPresenter
16:00StiCA Update ( 00:20 ) 1 file
16:20Vertex Fitting ( 00:20 ) 1 fileDmitri

EPD Data Analysis 2016 Run

Speaker : Rosi Reed


Talk time : 11:00, Duration : 00:25

psn0636

 CVS code is in  offline/paper/psn0636/

PWGC Meeting

2016-04-05 11:00
2016-04-05 12:30
America/New York
Tuesday, 5 April 2016
https://bluejeans.com/883580682/9067, at 15:00 (GMT), duration : 01:30
  --- Agenda April 5, 2016 ---

 

1) Study of Minuit Vertex Finder parameters in Run-14 Au+Au [Xin Dong]

  See Xin's blog: https://drupal.star.bnl.gov/STAR/blog/dongx/minuit-vf-parameter-study-run14-auau200-vpdmb-data

2) Test Production QA

 updates on status of test analyses taking place in PWGs
see e.g. http://www.star.bnl.gov/HyperNews-star/protected/get/starpwgc/4156/1/1/1.html


3) Review PWG_TASKS leases
https://drupal.star.bnl.gov/STAR/pwg/common/pwg-disk-quota-leases

 
 

4) Upcoming deadlines and conferences

 https://drupal.star.bnl.gov/STAR/pwg/common/upcoming-conferences-deadlines

 

 SQM abstracts: see https://drupal.star.bnl.gov/STAR/blog/geurts/star-2016-conference-contributions

 

5) AOB
 

 

Click on the following link for the  BlueJeans Connection Details for PWGC  Meetings 

SQM2016

Title: Measurement of correlation between different order flow harmonics and event plane angles in heavy-ion collision in STAR.

DIS 2016 - Talk

Trigger Board Meeting for Run16

2016-04-04 13:00
America/New York
Monday, 4 April 2016
BNL Physics 1-224 and SeeVogh (ID 101 6255), at 17:00 (GMT), duration : 00:00
 

STAR BUR writing committee 2016

2016-04-04 15:00
2016-04-04 16:30
America/New York
Monday, 4 April 2016
https://bluejeans.com/333205157, at 19:00 (GMT), duration : 01:30
 
Agenda: 

discussion of materials at hands 

default table of options: 
24 cryo-weeks, 19 cryo-weeks (baseline) and 15 cryo-weeks 

likely 2 weeks of CeC R&D for EIC (coherent electron cooling test) 
2.5 weeks of cool-down and machine commissioning 
from past experience and what CAD provided for switching to d+Au (0.5 weeks per switch) 

1) pp510 
    at least 10--11 weeks of operation  

2) isobars (Zr-96 and Ru-96) 

    Latest news from CAD is that Ru-96 with natural abundance 
    can achieve about 20% of the Au+Au luminosity, (10^9 ions per bunch) 
    This means that Au+Au luminosity is about 103x10^26cm^2s-1, x20%*5barns = 10KHz 
    average store luminosity is about 80% of that. 
    However, this is more than enough for our purpose. 

    If DAQ rate is 2000Hz, and we run at 95 hours per week, 
    this should provides us with 680 million events per week 

    1.5 weeks of Zr and Ru each with ~1 billion MB events (realistically 800M). 
    +0.5 weeks each for setup; 
     4 weeks of Isobar running 

3) possible 27GeV running for Lambda/lambdabar polarization 
    similar calculations, now luminosity goes down by a factor (27/200)^2 = 2% 
    This is 1800Hz 
    with a week running, 600million MB events 
    effectively, at least 1.5 weeks of running 

4) RHICf 
    two programs:  
    a) cross-section 
    b) A_N 
    each about 0.5 week 
    This is a separate request to PAC, but need to coordinate among RHICf and STAR 
    Sako is in our committee so that he knows what we are proposing. 


Cryo-weeks necessary for operation: 

MAXIMUM: 
    2.5+11+4+1.5+1.5 = 20.5 weeks + 2 (CeC) = 22.5 weeks 
    
MINIMUM: 
   a) 
    2.5+10 =12.5+2 = 14.5 weeks (just pp510 program) 
   b) 
    2.5+10+1=13.5+2=15.5 weeks (pp510 + RHICf) 
   c) 
    2.5+10+1+1.5 = 15+2 = 17 weeks (pp510+RHICf+27) 
   d) 
    2.5+10+1+4 = 17.5+2 = 19.5 weeks (pp510+RHICf+Isobar) 
   ???